Farmcrest-Kincaid 2022 Reconstruction Project Updates
Proposed Plans: Farmcrest & Kincaid Reconstruction
Amberley Village presented plans for the reconstruction of Farmcrest and Kincaid in resident meetings, held in December 2021 and June 2022. Residents who were unable to make one or both of the meetings can reference the video links, which capture both presentations. The PowerPoint presentations featured in each of the videos are also posted for reference. These have been positioned so the video and presentation can be viewed simultaneously. Please note that changes may yet occur due to weather, supply chain issues or personnel. Amberley Village will make every effort to communicate with residents throughout the project. Regular updates will also be posted to the website.
Farmcrest Reconstruction Update
11/11/2022: Amberley Village sent the following e-mail to residents who provided their information for inclusion in updates:
Update: Greater Cincinnati Water Works (GCWW) is in the process of tying in residential water service lines to the new water main, which was recently installed. GCWW is responsible for notifying individual households at least 24 hours in advance of the water being shut-off to connect each home. Notification is achieved through the use of door hangers, so be sure to check your front doors regularly to avoid missing your notice. Connection into the new water main can take up to ten hours, so be sure to plan ahead by purchasing or storing water for use during this time.
GCWW began the residential tie-ins for the homes on North Farmcrest last week. The crews began at the intersection of North and South Farmcrest, and will be working clockwise through the neighborhood until all homes along North and South Farmcrest have been connected to the new water main.
Once the GCWW water main project is finished, work on the Farmcrest Reconstruction Project will be suspended for the winter, as the winter weather is not conducive to the street reconstruction work.
Amberley Village is working to maintain regular contact with GCWW to bring you updates, however, due to the nature of construction projects, we are only able to share information as it becomes available to us. If you have specific questions or concerns regarding your property as it relates to the Farmcrest/Kincaid Water Main Project, please contact Greater Cincinnati Water Works directly at 513-765-1212.
|
7/1/2022: Work has begun on the storm water infrastructure replacement near the intersection of North and South Farmcrest Drive, with excavation and installation of a manhole and pipe on the property at 3109 North Farmcrest. Plans to install the storm water system on South Farmcrest have been redirected to install the system on North Farmcrest first as a precaution in case of heavy rains. The storm water system will be installed on South Farmcrest once installation on North Farmcrest is complete.
A resident meeting was held on Monday, June 20, 2022, where detailed plans for this project were shared. A tentative work schedule was presented, along with details regarding each phase of the project. These can be found by visiting the links below.
The update below was based upon a preliminary project planning meeting. As of May 11, 2022, no additional information is available, and contractors are still awaiting confirmation on arrival of materials. Please check back for updates.
Questions?
Please Email.
Helpful Resources
- Farmcrest Kincaid Tentative Construction Schedule 2022
- North Farmcrest South Farmcrest Kincaid Road 2022
- North Farmcrest South Farmcrest Kincaid Road Presentation 2021
- Farmcrest Reconstruction Meeting Video 2022
- Farmcrest Reconstruction Project Meeting Video 2021
- June 2022 Meeting Photo Gallery
- 2022-23 Farmcrest-Kincaid Reconstruction Project Photo Gallery